The track and roadbeds
of the Corregidor Rail System were built to
best practice standards as the new lines were envisioned to be the permanent
rail system for the island. Overhead
wires were constructed and carried 600 volts of direct current electricity.
The lines connecting the batteries were also rigged with overhead wires
as part of the electrification program of the entire island.
Once the batteries had been filled with their stores (projectiles,
powder, other heavy supplies), the power lines were disconnected using junction
switches when the lines were idle.

Compared to the early railroad track
length (3,800 feet), the new electric line needed 14,700 feet of track to reach
Topside. This length was needed
because it wound up the steep curves and banks. In all, the track length was
estimated to complete six complete circles but the average grade was only 3.4%.
The electric line started at the
Tony Feredo